CNC part leak-test acceptance requires a defined test boundary, an application-based leakage limit, stated units and conditions, and evidence that the fixture and test system can distinguish an acceptable part from an unacceptable one. A report that only says “air test passed” leaves too many questions unanswered: which passages were tested, what was sealed temporarily, and how was the result evaluated?
For buyers ordering manifolds, housings or fluid-handling components through CNC machining services, the useful deliverable is a repeatable acceptance agreement. This FUMING guide explains what to include before quotations are compared. It does not prescribe a universal pressure or leakage limit; those must come from the component’s design requirements and the approved test method.
Define the failure you need to prevent
Begin with a simple drawing showing where the working medium belongs and where it must not go. Leakage to the outside, ingress from the environment and crossover between two internal circuits are different failure modes. A setup that checks one does not automatically cover the others. Record whether the delivered item is a bare machined body, a plugged subassembly or a fully sealed product.
INFICON’s guidance on setting a leak-rate specification starts with the failure mechanism and application conditions. That is a stronger basis than copying a limit from an unrelated component. The test gas, service medium, pressure difference and temperature conditions must be understood before results from different methods are treated as equivalent.
Ask the responsible design engineer to identify the acceptance authority. The purchasing team can make the requirement explicit, but should not invent a leakage allowance simply because a supplier’s tester offers a convenient preset. If the end product has a regulated or customer-specific requirement, reference its controlled document and revision rather than translating it informally into a workshop note.
Draw the boundary between the part and the fixture
A temporary test fixture adds its own seals, fittings, tubing and trapped volume. Mark each connection on the test sketch. State which plugs are production components and which are temporary closures. Identify seals that contact a machined face, a thread, an O-ring groove or a bore. This makes it possible to discuss whether the setup covers the feature that matters in service.
Consider an illustrative manifold with two independent channels. Pressurizing both channels together may not reveal communication between them. The approved plan should say how each required boundary is challenged and monitored. This is an engineering review example, not a recommended test sequence for every manifold.

Fixture drawings should also identify replaceable seals and their approved condition. When a failed part passes after a fixture seal is changed, retain both results and the maintenance record. Do not silently overwrite the failure or conclude that the part was defective before the fixture was investigated. Conversely, a passing fixture check does not resolve a damaged sealing face on the component.
Keep leak acceptance connected to the quality assurance plan. Dimensional inspection, surface condition and functional leakage evidence answer related but separate questions. A drawing-compliant groove does not by itself prove that the specified assembly boundary is leak-tight.
Specify the result together with its test conditions
| Agreement field | What the buyer should request | Ambiguity it removes |
|---|---|---|
| Component state | Part number, revision, processing stage and fitted components | Whether the test applies to the delivered configuration |
| Boundary | Ports, circuits, temporary closures and fixture drawing revision | Which leak paths were actually included |
| Test conditions | Medium, pressure reference, temperature condition and method revision | Whether two reported results can be compared |
| Acceptance result | Quantity, units, limit and decision rule | Whether a number represents pressure change or leak rate |
| System verification | Reference checks, equipment identity and validity records | Whether a passing display is supported by a functioning setup |
| Traceability | Part or lot identity, test time and retained result | Which shipped items the evidence covers |
Write units in full in the approved specification. If a flow value is normalized to reference conditions, identify those conditions. If the instrument reports a pressure change over a measurement interval, retain the interval and relevant setup definition. A pressure drop and a volumetric leakage rate are not interchangeable labels.
Separate functional leakage testing from proof-pressure or structural qualification requirements. One acceptance record should not be described as evidence for another test unless the approved engineering specification explicitly establishes that relationship. Equipment selection and safe pressure limits belong in a qualified test plan.
Control stabilization and reference checks
For pressure-decay testing, the timing and thermal state are part of the measurement. INFICON’s automotive testing overview describes temperature changes as a source of difficulty for pressure-based measurements. A result taken immediately after a warm cleaning or machining operation should not be compared casually with one from a stabilized receiving laboratory.
The procurement requirement can therefore ask the test provider to document its conditioning rule and validated cycle. Record the relevant process stage, delay before testing and environmental conditions required by that method. Do not impose an arbitrary universal waiting period. The acceptable rule depends on the part, fixture and detection task.
CTS’s pressure-decay calibration example uses a non-leaking master and a leak standard at the intended pressure with repeatable cycle timing. This illustrates why the reference setup matters. It is not a reason to assume every tester uses the same calibration sequence or conversion.

For a purchased test service, request equipment and reference-device identification, the applicable calibration or verification status, and the system check results required by the agreed procedure. Distinguish instrument calibration from a check of the assembled fixture and recipe. A current instrument certificate alone does not describe whether a particular port was accidentally left outside the test boundary.
Make failed results useful instead of disposable
A useful record retains the first result, the reason for any retest, the intervention performed and the final disposition. Distinguish part rework from fixture maintenance and from an invalid test cycle. If a component is cleaned again, a plug is replaced or a sealing surface is repaired, keep that change linked to the same part identity.
For an initial order, ask for representative raw results and a completed report example before accepting only a batch summary. Agree how the sampling plan relates to the delivered quantity and what happens when a sampled item fails. Do not infer that every item was tested from a certificate that only names the batch.
The related CNC cleanliness acceptance checklist is useful when cleaning and packaging affect the delivered condition. Keep the two acceptance records separate: a clean passage can leak, and a sealed passage can still contain unacceptable contamination.
Questions to close before releasing the purchase order
Can we specify “zero leakage”?
Use a measurable requirement tied to a defined method and detection capability. An unqualified phrase gives neither supplier nor buyer a practical decision rule. Have the design authority translate the functional need into an approved acceptance criterion.
Does a passing air test prove liquid performance?
Only an established relationship for the particular application can support that conclusion. Retain the actual test medium and conditions on the report, and ask the responsible engineer to approve any correlation used for service acceptance.
Should we repeat the test after finishing?
Decide this in the process plan. If surface finishing, assembly or another subsequent operation could affect the specified boundary, identify the final acceptance stage explicitly. Do not assume an earlier result automatically covers later processing.
To discuss a CNC component with FUMING, send the drawing, circuit sketch and existing leak-test specification. Include the required delivered configuration and reporting format so the test scope and any specialist verification needs can be reviewed before quotation.